Photos provided by Monte Bartek of Bartek Recon
Aerial Photos of New Sevier County Medical Center Construction Site
Photos provided by Monte Bartek of Bartek Recon.
Aerial Views of the New Sevier County Medical Center Under Construction
Aerial photos provided by Monte Bartek of Bartek Recon.
Aerial Photos of the New Sevier Medical Center Under Construction
Aerial Photos provided by Monte Bartek of Bartek Recon
Aerial Photos of Construction at the New Sevier County Medical Center in SW AR
Photos by Monte Bartek of Bartek Recon
New Hospital Construction Project in Sevier County, Arkansas
Photos by Monte Bartek of Bartek Recon
Aerial Photos of Construction Site at the New Sevier County Medical Center
Photos are provided by Monte Bartek of Bartek Recon.
Aerial Views of Construction Site at the New Sevier County Medical Center
Aerial Photos courtesy of Bartek Recon
Latest Aerial Photos at the Construction Site of the New Sevier County Medical Center
Latest Progress Report From the Construction Site of the New Sevier County Medical Center
Contract Days: 485; Days Remaining: 227; Percent Complete: 53.02%
PERSONNEL ONSITE:
• Four (4) Prime Contractors:
o Gigerich Electrical
o Bass Concrete
o Car-Son Construction
o DS Murphy (Metal Building Erector)
• Three (3) Structural Steel Erectors
• Two (2) Electricians
EQUIPMENT ONSITE:
• Five (5) Scissor Lifts
• One (1) Takeuchi Mini Excavator
• One (1) Takeuchi Skid Steer
• One (1) Komat’su Excavator
• One (1) Gradall Shooting Boom Forklift
• One (1) Grove Crane
• One (1) Welding Machine
WORK IN PROGRESS:
a. Building “A”:
i. Structural Steel:
1. Steel decking and miscellaneous screen steel is being erected at the roof level.
2. The steel platforms for the roof top units (RTU’s) are being
completed in preparation to pour the concrete support pads. See
the discussion in the discussion section below.
3. Steel decking is being completed on the high roof.
ii. Electrical:
1. Uni-Strut framing is being erected at the roof top unit (RTU)
locations
New Sevier County Medical Center Latest Aerial Photos
Photos provided by Monte Bartek of Bartek Recon
Latest Aerial Photos of Construction on the New Sevier County Medical Center
Photos by Monte Bartek of Bartek Recon
VIDEO: Senator John Boozman at the New Sevier County Medical Center Construction Site on Monday
VIDEO: Construction Site Progress of New Sevier County Medical Center
Progress continues at the construction site of the new Sevier County Medical Center.
Aerial Views at Construction Site of New Sevier County Medical Center
Despite the recent rains, progress is being made at the construction site of the new Sevier County Medical Center.
(Photos courtesy of Monte Bartek)
Progress from the Construction Site of the New Sevier County Medical Center
The latest progress report from the Sevier County Medical Center construction site
PERSONNEL ONSITE:
• Four (4) Prime Contractors Onsite:
o Gigerich Electrical
o Bass Concrete
o Middleton Plumbing
o Car-Son Construction
• Three (3) Electricians
• Five (5) Concrete Workers
• Six (6) Plumbers
• Seven (7) Structural Steel Erectors
EQUIPMENT ONSITE:
• One (1) SkyJack Scissor Lift
• One (1) Bobcat Mini Excavator
• Three (3) Takeuchi Mini Excavators
• One (1) Dynapac Smooth Drum Compactor
• One (1) Backhoe
• One (1) Komat’su Excavator
• One (1) Caterpillar Excavator
• One (1) Bigge Grove Crane
• One (1) Gradall Shooting Boom Forklift
STORED MATERIALS:
• Reinforced Concrete Pipe (RCP)
• Polyethylene Piping
• PVC Conduit
• Rigid Steel Conduit Fittings
WORK IN PROGRESS:
1. Storm Water Pollution Prevention Plan (SWPPP):
a. The SWPPP remains as previously reported.
2. Site:
a. Underground electrical risers are being installed as shown on E0.01 Electrical
Site, PR#005, dated 04-07-21.
3. Building:
a. Building “A”:
i. The south half of the slab has been poured.
ii. Structural steel is being erected at the northwest corner of the building.
Columns and some beams have been erected.
iii. Concrete footings are being poured at Grid H.7.
b. Building “B”:
i. The under-slab sanitary sewer piping has been installed. Due to the excessive rain the contractor has removed the excavated, engineered fill and installed SB-2 for the purposes of time required to aerate and dry the excessive wet material excavated from the plumbing trenches.
ii. Most of the electrical conduit has been installed; a few conduit risers and conduit runs to be stubbed out of the building remain to be completed.
Latest Aerial Photos of Construction of New Sevier County Medical Center
Progress at the construction site of the Sevier County Medical Center. (Aerial photos compliments of Monte Bartek)
Aerial Photos of New Sevier County Medical Center Construction Site
Photos Courtesy of Monte Bartek
Recent Construction Site Aerial Photos of the New Sevier County Medical Center
. (Pictures courtesy of Monte Bartek)