Sevier County Medical Center

Lady Colts Basketball Team Pictured with Congressman Bruce Westerman

Members of the Lady Colts basketball team took some time on Monday afternoon to visit with Arkansas' 4th District Congressman Bruce Westerman at the construction site of the Sevier County Medical Center.

Members of the Lady Colts basketball team took some time on Monday afternoon to visit with Arkansas' 4th District Congressman Bruce Westerman at the construction site of the Sevier County Medical Center.

Lori House, CEO of the new Sevier County Medical Center, was Guest Speaker at De Queen Lions Club

Lori House, CEO of the new Sevier County Medical Center, was Tuesday’s guest speaker at the De Queen Lions Club. Lion Jeff Brown introduced House.

lions lori.jpg

Latest Aerial Photos at the Construction Site of the New Sevier County Medical Center

Latest Progress Report From the Construction Site of the New Sevier County Medical Center

Contract Days: 485; Days Remaining: 227; Percent Complete: 53.02%

PERSONNEL ONSITE:

• Four (4) Prime Contractors:

o Gigerich Electrical

o Bass Concrete

o Car-Son Construction

o DS Murphy (Metal Building Erector)

• Three (3) Structural Steel Erectors

• Two (2) Electricians

EQUIPMENT ONSITE:

• Five (5) Scissor Lifts

• One (1) Takeuchi Mini Excavator

• One (1) Takeuchi Skid Steer

• One (1) Komat’su Excavator

• One (1) Gradall Shooting Boom Forklift

• One (1) Grove Crane

• One (1) Welding Machine

WORK IN PROGRESS:

a. Building “A”:

i. Structural Steel:

1. Steel decking and miscellaneous screen steel is being erected at the roof level.

2. The steel platforms for the roof top units (RTU’s) are being

completed in preparation to pour the concrete support pads. See

the discussion in the discussion section below.

3. Steel decking is being completed on the high roof.

ii. Electrical:

1. Uni-Strut framing is being erected at the roof top unit (RTU)

locations